TeraWulf gets Google credit support for $19B Anthropic data center lease in Kentucky
TeraWulf said Nov. 4 it signed credit support agreements with Google to back debt financing for about $19 billion in Anthropic lease commitments at its Hawesville, Kentucky campus. It also signed a Fluor construction agreement for three buildings, priced at a guaranteed maximum still being set. Phased service starts late 2027 and runs through Q2 2028.